Neurath Lignite Power Station

Neurath Lignite Power Station show reference
Neurath Lignite Power Station

Services

  • Detailed engineering work on the order
  • Thermal and acoustic insulation for the steam generator blocks of the world’s largest lignite coal power station
  • Work on the electric filter and flue-gas clean-up systems
  • 280 insulation assemblers
  • 540,000 m2 of mineral wool, 2,320 tons of steel sheeting
  • Total area insulated: 270,000 m2

Task

We executed work on the thermal and acoustic insulation fitted to the steam generators at the two new blocks of the world’s largest lignite-fuelled power station in Neurath/Grevenbroich, Germany, for the Alstom/Hitachi syndicate. Additional work was performed on the electric filter and flue-gas clean-up systems as well as the heat transfer system. The contract also entailed engineering and the assembly of the trace heating system. We performed our work over a period of 36 months, completing the project ahead of schedule.

Neurath Lignite Power Station

Services

  • Detailed engineering work on the order
  • Thermal and acoustic insulation for the steam generator blocks of the world’s largest lignite coal power station
  • Work on the electric filter and flue-gas clean-up systems
  • 280 insulation assemblers
  • 540,000 m2 of mineral wool, 2,320 tons of steel sheeting
  • Total area insulated: 270,000 m2

Task

We executed work on the thermal and acoustic insulation fitted to the steam generators at the two new blocks of the world’s largest lignite-fuelled power station in Neurath/Grevenbroich, Germany, for the Alstom/Hitachi syndicate. Additional work was performed on the electric filter and flue-gas clean-up systems as well as the heat transfer system. The contract also entailed engineering and the assembly of the trace heating system. We performed our work over a period of 36 months, completing the project ahead of schedule.

Services

  • Detailed engineering work on the order
  • Thermal and acoustic insulation for the steam generator blocks of the world’s largest lignite coal power station
  • Work on the electric filter and flue-gas clean-up systems
  • 280 insulation assemblers
  • 540,000 m2 of mineral wool, 2,320 tons of steel sheeting
  • Total area insulated: 270,000 m2

Task

We executed work on the thermal and acoustic insulation fitted to the steam generators at the two new blocks of the world’s largest lignite-fuelled power station in Neurath/Grevenbroich, Germany, for the Alstom/Hitachi syndicate. Additional work was performed on the electric filter and flue-gas clean-up systems as well as the heat transfer system. The contract also entailed engineering and the assembly of the trace heating system. We performed our work over a period of 36 months, completing the project ahead of schedule.

Walsum Pit-Coal Boiler

Walsum Pit-Coal Boiler show reference
Walsum Pit-Coal Boiler

Services

  • Completed in only 86 days
  • 180 insulation specialists working around the clock
  • Approx. 14,000 m2 of boiler insulation
  • 40,000 m2 of mineral wool
  • 20,000 m2 of steel sheeting
  • 1,350 m2 of piping

Task

BILFINGER OKI Isoliertechnik was awarded a contract by Babcock Borsig Steinmüller GmbH to provide thermal insulation for the pit coal-fired boiler of Block 10 of the power station in Walsum. The team of 180 insulation experts worked around the clock, even at Christmas, to complete the project on time.

Walsum Pit-Coal Boiler

Services

  • Completed in only 86 days
  • 180 insulation specialists working around the clock
  • Approx. 14,000 m2 of boiler insulation
  • 40,000 m2 of mineral wool
  • 20,000 m2 of steel sheeting
  • 1,350 m2 of piping

Task

BILFINGER OKI Isoliertechnik was awarded a contract by Babcock Borsig Steinmüller GmbH to provide thermal insulation for the pit coal-fired boiler of Block 10 of the power station in Walsum. The team of 180 insulation experts worked around the clock, even at Christmas, to complete the project on time.

Services

  • Completed in only 86 days
  • 180 insulation specialists working around the clock
  • Approx. 14,000 m2 of boiler insulation
  • 40,000 m2 of mineral wool
  • 20,000 m2 of steel sheeting
  • 1,350 m2 of piping

Task

BILFINGER OKI Isoliertechnik was awarded a contract by Babcock Borsig Steinmüller GmbH to provide thermal insulation for the pit coal-fired boiler of Block 10 of the power station in Walsum. The team of 180 insulation experts worked around the clock, even at Christmas, to complete the project on time.